FMDB Weekly #14 (Apr 4 - April 8)

Added by E. Seegyoung Seol over 6 years ago

[ Week 14 Activities ]

FMDB

  • constraint: single part per mesh
  • (on-going) entity set and entity group integration
    - mesh migration
    - distributed entity set file I/O
  • (on-going) ghosting
    - N-layer creation
    - layer accumulation
    - mesh verification
    - thesis writeup
  • (on-going) FMDB.h development
    - missing api functions (region creation, entity search, etc)
  • (on-going) User's Guide update

iMesh/iMeshP

  • (completed) iMesh_FMDB development
    - iMesh compliance test passed
  • (on-going) memory leak w/ valgrind
  • (on-going) iMeshP_FMDB development
  • (on-going) build issues (fortran support, name mangling, etc.)

SCUtil/iBase

  • NONE

GRM/iRel

  • NONE

[ Planned Week 15 Activities ]

FMDB v1.2

  • FMDB.h development
  • entity set/entity group integration
  • ghosting development
  • parallel code improvement (cleanup, performance, etc.)

iMesh/iMeshP

  • memory leak debugging w/ valgrind (serial)
  • iMeshP_FMDB development

GMI/iGeom

  • autotool support (iGeom-Defs.inc, fortran, etc.)
  • iGeom status (implementation/testing) review

SCUtil/iBase

  • NONE

GRM/iRel

  • NONE

[ Independent Study ]

  • C++ Templates
  • Design Pattern

[ Remarks ]

  • FMDB team meeting: Wednesday 11am-12pm
  • ITAPS telecon: Thursday 12pm-1pm
  • iMeshP compliance test verification with FMDB pended due to incomplete implementation such as ghosting & multiple part per process
  • entity group migration with "splitted" entity data stream won't be considered to put into the repository
    Instead, better algorithm for migration procedure will be investigated.